C2F Construction Process

Step 1: Make Ready Engineering

Examine existing infrastructure and create design sheets. Timeline: 18 weeks. 

Step 2: Make Construction Ready

Make plans to get existing infrastructure ready for adding fiber lines. Timeline: 18 weeks. 

Step 3: Construction

Bury fiber cable underground and string it from poles to build the network that connects homes to our fiber hut. Timeline: up to 14 weeks. 

Step 4: Splicing

Splice the necessary cables at each end point and mount splices in enclosures secured to distribution poles. Timeline: up to 14 weeks. 

Step 5: Service Drop

Extend the fiber cable from the nearest splice point to the area receiving service. Timeline: approximately 6 weeks. 

Step 6: Installation

Once the fiber network is ready, the team will hook up homes and businesses to receive high-speed internet service. 

Step 1: Make Ready Engineering

Examine existing infrastructure and create design sheets. Timeline: 18 weeks.

Step 2: Make Construction Ready

Make plans to get existing infrastructure ready for adding fiber lines. Timeline: 18 weeks.

Step 3: Construction

Bury fiber cable underground and string it from poles to build the network that connects homes to our fiber hut. Timeline: up to 14 weeks.

Step 4: Splicing

Splice the necessary cables at each end point and mount splices in enclosures secured to distribution poles. Timeline: up to 14 weeks.

Step 5: Service Drop

Extend the fiber cable from the nearest splice point to the area receiving service. Timeline: approximately 6 weeks.

Step 6: Installation

Once the fiber network is ready, the team will hook up homes and businesses to receive high-speed internet service.