Step 1: Make Ready Engineering
Examine existing infrastructure and create design sheets. Timeline: 18 weeks.
Step 2: Make Construction Ready
Make plans to get existing infrastructure ready for adding fiber lines. Timeline: 18 weeks.
Step 3: Construction
Bury fiber cable underground and string it from poles to build the network that connects homes to our fiber hut. Timeline: up to 14 weeks.
Step 4: Splicing
Splice the necessary cables at each end point and mount splices in enclosures secured to distribution poles. Timeline: up to 14 weeks.
Step 5: Service Drop
Extend the fiber cable from the nearest splice point to the area receiving service. Timeline: approximately 6 weeks.
Step 6: Installation
Once the fiber network is ready, the team will hook up homes and businesses to receive high-speed internet service.